Sunday 30 August 2020

403 INFRASTRUCTURE PROJECTS SHOW COST OVERRUNS AND 530-TIME OVERRUN: MOSPI REPORT

403 INFRASTRUCTURE PROJECTS SHOW COST OVERRUNS AND 530-TIME OVERRUN: MOSPI REPORT 

  • This is out of 1,686 projects worth Rs 150 crore and above. 
    • Overall cost overrun is about 19.60% of the original cost and the average time overrun is around 41.16 months. 
    • Presently, the Ministry of Statistics and Programme Implementation (MOSPI) monitors infrastructure projects worth Rs 150 crore and above. 
  • Reasons for these overrun 
    • Delay in land acquisition, forest/environment clearances, and lack of infrastructure support & linkages. 
    • Project financing issues leading to delay in finalization of detailed engineering etc. 
    • Delay in tendering, ordering, and equipment supply. 
    • No reporting of revised cost estimates leading to under-reporting. 
    • Law and order problems, geological surprises 
  • Suggestions 
    • Improving processes and capabilities: By investing in pre-planning and site investigation, reforming procurement, strengthening contract management, collaborative planning, etc. 
    • Strengthen people management processes i.e. Clear responsibility charter with a delegation of the decision-making process, adopting technology, Overcoming legacy challenges. 
    • Deepening stakeholder management for land acquisition and regulatory approvals. 
  • Steps were taken in this direction: Preparing National Infrastructure Pipeline which aims to improve project preparation, Project Development Cells in Ministries, revised Model Concession agreement for Build-Operate-Transfer (BOT) model, etc. 

No comments: