403 INFRASTRUCTURE PROJECTS SHOW COST OVERRUNS AND 530-TIME OVERRUN: MOSPI REPORT
403 INFRASTRUCTURE PROJECTS SHOW COST OVERRUNS AND 530-TIME OVERRUN: MOSPI REPORT
- This is out of 1,686 projects worth Rs 150 crore and above.
- Overall cost overrun is about 19.60% of the original cost and the average time overrun is around 41.16 months.
- Presently, the Ministry of Statistics and Programme Implementation (MOSPI) monitors infrastructure projects worth Rs 150 crore and above.
- Reasons for these overrun
- Delay in land acquisition, forest/environment clearances, and lack of infrastructure support & linkages.
- Project financing issues leading to delay in finalization of detailed engineering etc.
- Delay in tendering, ordering, and equipment supply.
- No reporting of revised cost estimates leading to under-reporting.
- Law and order problems, geological surprises
- Suggestions
- Improving processes and capabilities: By investing in pre-planning and site investigation, reforming procurement, strengthening contract management, collaborative planning, etc.
- Strengthen people management processes i.e. Clear responsibility charter with a delegation of the decision-making process, adopting technology, Overcoming legacy challenges.
- Deepening stakeholder management for land acquisition and regulatory approvals.
- Steps were taken in this direction: Preparing National Infrastructure Pipeline which aims to improve project preparation, Project Development Cells in Ministries, revised Model Concession agreement for Build-Operate-Transfer (BOT) model, etc.